image

Katsonga Girls Hostel fence

A fence for Katsonga girls hostel

for security

Start date: 2022-01-01 Due date: 2022-08-30 Approval date: 2021-09-08
40,612,245.10   MWK
Total Funding
2022-08-19
Date Created
2022-08-19
Last updated
Construction
Project Type
Completion
Project Status
Absence of a clear feasibility study Unrealistic budgets Limited assessment of environmental impacts Limited assessment of social impacts Limited assessment of economic impacts Weak stakeholder engagement Change of scope Cost overruns and budget inflation Lack of transparency in procurement processes Limited competition Favoritism in bidding processes Political interference Weak accountability mechanisms Frequent project delays (time overruns) Environmental violations Social violations Lack of maintenance plans Under-utilization of project Abandonment of project

Locations

Description katsonga girls secondary school
District Zomba
Region Southern
Street address
Postal code

Documents

Title the contract for construction of Kasonga girls hostel fence at Malosa constituency- Kasonga ward
Description signed contract betweent Zomba District Council and Prichala Civil Engineering
Document Type Signed Contract
Date Published 2021-12-01
Date Modified 2021-12-01
Language
Page Start
Page End
Author zomba district council
Access Details
Title contract negotiations on construction of Katsonga girls hostel fence
Description contract negotiations on construction of Katsonga girls hostel fence in Malosa constituency
Document Type Negotiation Parameters
Date Published 2021-12-24
Date Modified 2021-12-24
Language
Page Start
Page End
Author zomba district council
Access Details
Title Award of offer for construction of Katsonga girls hostel fence
Description award of offer for contsruction of Katsonga girls hostel fence in Malosa constituency
Document Type Award notice
Date Published 2021-11-29
Date Modified 2021-11-29
Language
Page Start
Page End
Author zomba district council
Access Details

Parties

No records were added

Contracts

No records were added

Budget

No records were added

Project Funding

No records were added
No comments added

Environment

No record was added

Completion

End Date: 2022-08-30
End Details: fully constructed hostel fence
Final Scope: brick fence
Final Scope Details:
Final Value Amount: MWK 40,612,245.10
Final Value Details:

Finances

No records were added

Milestones

No records were added

Transactions

No records were added

Benefits

No records were added

Additional Classifications

No records were added

Social

No records were added

Metrics & Forecasts

No records were added

Policy

No record was added

Timelines

Asset Life Time

Start Date 2022-08-31
End Date 2042-08-31
Max End Date

© 2025, Construction Sector Transparency Initiative (CoST Malawi). All Right Reserved;