Construction of Single Lane Bridge along Likangala River

Single Concrete Deck Bridge

The Bridge has been constructed along as part of evacuation route reaching Multipurpose Evacuation Centre in Chambo ward

Start date: 2021-10-08 Due date: 2022-08-31 Approval date: 2021-02-26
75,573,550.00   MWK
Total Funding
2022-08-29
Date Created
2022-08-29
Last updated
Construction
Project Type
Implementation
Project Status
Absence of a clear feasibility study Unrealistic budgets Limited assessment of environmental impacts Limited assessment of social impacts Limited assessment of economic impacts Weak stakeholder engagement Change of scope Cost overruns and budget inflation Lack of transparency in procurement processes Limited competition Favoritism in bidding processes Political interference Weak accountability mechanisms Frequent project delays (time overruns) Environmental violations Social violations Lack of maintenance plans Under-utilization of project Abandonment of project

Locations

Description Construction of Single lane Bridge along Likangala River
District Zomba
Region Southern
Street address Manda a akaidi in Chambo
Postal code 0000

Documents

Title BoQ
Description BoQ from successful bidder
Document Type Bill of quantity
Date Published 2021-09-28
Date Modified 2021-09-28
Language eNGLISH
Page Start 1
Page End 3
Author OXFAM
Access Details

Parties

Description Adaptation Fund
Locality Washington, DC
Region District of Columbia
Street address Adaptation Fund Postal Address Adaptation Fund Board Secretariat c/o Global Environment Facility Mail stop: N 7-700 1818 H Street NW Washington DC 20433 USA
Postal code 20433
Country Malawi
Telephone +1.202.473.0701
Fax Number +1.202.522.3240
URL https://www.adaptation-fund.org/
Description The Adaptation Fund finances projects and programmes that help vulnerable communities in developing countries adapt to climate change. Initiatives are based on country needs, views and priorities. Since 2010, the Adaptation Fund has committed US$ 923.5 million to projects and programmes to date, including 132 concrete projects. This spans nearly 100 countries, including 15 small island developing states and 30 least developed countries, serving about 36 million total beneficiaries. It also pioneered Direct Access, empowering countries to access funding and develop projects directly through accredited national implementing entities. Climate change is predicted to greatly affect the poorest people in the world, who are often hardest hit by weather catastrophes, desertification, and rising sea levels, but who have contributed the least to the problem of global warming. In some parts of the world, climate change has already contributed to worsening food security, reduced the predictable availability of fresh water, and exacerbated the spread of disease and other threats to human health. Helping the most vulnerable countries and communities is an increasing challenge and imperative for the international community, especially because climate adaptation requires significant resources beyond what is already needed to achieve international development objectives. The Fund is financed largely by government and private donors, and also from a two percent share of proceeds of Certified Emission Reductions (CERs) issued under the Protocol’s Clean Development Mechanism projects.
Description Dawn Construction Engineering
Locality Lilongwe
Region Central Region
Street address P.O. Box 30182, Lilongwe
Postal code 0000
Country Malawi
Email 0000
Telephone +265884055837
Fax Number
URL 0000
Description A registered civil contractor in the K1.0 Billion category
Description ZOMBA CITY COUNCIL
Locality Zomba City
Region Southern Region
Street address Off Nkulichi Road Opposite State House
Postal code 0000
Country Malawi
Telephone 0993383671
Fax Number 01525367
URL 0000
Description
Description Suida and Partners
Locality Blantyre
Region Southern Region
Street address P.O. Box 32345, Chichiri
Postal code 0000
Country Malawi
Email 0000
Telephone +265888343523
Fax Number
URL 0000
Description Registered consulting engineers

Contracts

OCID TD-OX/ZCC/21/172/LLW-MW/007/A
External Reference
Title Construction of Single Lane Bridge along Likangala River
Description Extension period
Status Active
Contract Value MWK 75,573,550.00
Cost Estimate MWK 75,573,550.00
Final Value 0.00
Start Date 2021-10-08
End Date 2022-03-27
Max Extent Date 2022-06-27
Duration In Days 262
Procurement Method Open
Method Details Best proposal
Procuring Entity ZOMBA CITY COUNCIL-Zomba City-MW
Administrative ZOMBA CITY COUNCIL-Zomba City-MW

Documents

No records were added

Modifications

No records were added

Budget

Description Construction of Single lane Bridge along Likangala River
Amount MWK 75,573,550.00
Start Date 2021-10-08
End Date 2022-03-27
Max Extent Date 2022-06-27
Duration In Days 262
Party ID Dawn Construction Engineering-Lilongwe-MW
URI

Project Funding

No records were added
No comments added

Environment

No record was added

Completion

End Date:
End Details:
Final Scope:
Final Scope Details:
Final Value Amount: 0.00
Final Value Details:

Finances

No records were added

Milestones

No records were added

Transactions

No records were added

Benefits

No records were added

Additional Classifications

No records were added

Social

No records were added

Metrics & Forecasts

No records were added

Policy

No record was added

Timelines

Asset Life Time

Start Date 2022-08-31
End Date 2042-08-31
Max End Date 2045-08-31