Absence of a clear feasibility study
Limited assessment of environmental impacts
Limited assessment of social impacts
Limited assessment of economic impacts
Weak stakeholder engagement
Limited competition
Frequent project delays (time overruns)
Lack of maintenance plans
Description
NOCMA formed in line with the National Energy Policy of January 2003, NOCMA was registered on 14thDecember 2010 under the companies Act of 1984.
With our head office in Kang’ombe House in City Centre in Malawi’s capital Lilongwe, we have an office at Mwanza border post and have operations through an agent at Songwe border to handle incoming fuel tankers.
Contracts
OCID
NOCMA/NCB/W/LL/2018/1
External Reference
Title
CONSTRUCTION AND INSTALLATION OF RAIL SIDING PUMP HOUSE AND ASSOCIATED EQUIPMENT AT LILONGWE AND BLANTYRE DEPOT
Description
construction and installation of Rail siding pump house and associated equipment at Lilongwe and Blantyre Depots
Status
Active
Contract Value
MWK 4,012,176,750.50
Cost Estimate
MWK 4,000,000,000.00
Final Value
0.00
Start Date
2018-12-31
End Date
2022-11-15
Max Extent Date
2022-12-31
Duration In Days
1461
Procurement Method
Open
Method Details
Best value to government
Procuring Entity
National Oil Company of Malawi (NOCMA)-Lilongwe-MW
Administrative
National Oil Company of Malawi (NOCMA)-Lilongwe-MW
Documents
No records were added
Modifications
No records were added
Budget
Description
Overall project budget
Amount
MWK 4,012,176,750.50
Start Date
2018-12-31
End Date
2022-11-30
Max Extent Date
2022-12-31
Duration In Days
1461
Party ID
National Oil Company of Malawi (NOCMA)-Lilongwe-MW
URI
Project Funding
Party
Malawi Government-Lilongwe-MW
Amount
MWK 4,012,176,750.50
Description
Currently NOCMA is financing the project from its own internal resources and it will later claim the paid amounts from the Storage/SFR Levy from the petroleum price build up.