Construction of a 30 tonne concrete deck bridge at Kanjamwana

Return
image

Construction of a 30 tonne concrete deck bridge at Kanjamwana

construction of a 30 tonne concrete deck bridge

to improve the quality of transportation during rainy season

Start date: 2023-01-13 Due date: 2023-05-13 Approval date: 2022-03-23
59,250,000.00   MWK
Total Funding
2023-03-10
Date Created
2025-03-12
Last updated
Construction
Project Type
Implementation
Project Status
Absence of a clear feasibility study Unrealistic budgets Limited assessment of environmental impacts Limited assessment of social impacts Limited assessment of economic impacts Weak stakeholder engagement Change of scope Cost overruns and budget inflation Lack of transparency in procurement processes Limited competition Favoritism in bidding processes Political interference Weak accountability mechanisms Frequent project delays (time overruns) Environmental violations Social violations Lack of maintenance plans Under-utilization of project Abandonment of project

Locations

Description T/A Kalumbu
District Lilongwe
Region Central
Street address
Postal code

Documents

Title Construction of a 30 tonne concrete deck bridge at Mwanang'ombe River on Mkomba to Chikanda road
Description the signed contract document
Document Type Signed Contract
Date Published
Date Modified
Language
Page Start
Page End
Author
Access Details

Parties

Description Lilongwe District Council
Locality Post Office Box 93, Lilongwe
Region Central
Street address Lilongwe
Postal code 0000
Country Malawi
Telephone 09000000000
Fax Number
URL
Description
Description Samwamwa civil engineering
Locality Lilongwe
Region
Street address Lilongwe
Postal code
Country Malawi
Email hsshsj@yahoo
Telephone 00000
Fax Number
URL
Description
Description Samwamwa civil engineering
Locality Lilongwe
Region
Street address Lilongwe
Postal code
Country Malawi
Email hsshsj@yahoo
Telephone 00000
Fax Number
URL
Description

Contracts

No records were added

Budget

Description CONSTRUCTION OF KANJAMWANA BRIDGE
Amount MWK 58,999,475.60
Start Date 2023-01-13
End Date 2023-04-13
Max Extent Date 2023-06-30
Duration In Days 168
Party ID Samwamwa civil engineering-Lilongwe-MW
URI NA
Description CONSTRUCTION OF KANJAMWANA BRIDGE
Amount MWK 58,999,475.60
Start Date 2023-01-13
End Date 2023-04-13
Max Extent Date 2023-06-30
Duration In Days 168
Party ID Samwamwa civil engineering-Lilongwe-MW
URI NA

Project Funding

No records were added
No comments added

Environment

No record was added

Completion

End Date: 2023-10-03
End Details: the project has been completed
Final Scope: construction of 6 cell box culvert with retaining walls with associated works
Final Scope Details: the scope was modified due to the prevailing site conditions
Final Value Amount: MWK 58,094,784.98
Final Value Details: the revision in scope lowered the cost

Finances

No records were added

Milestones

No records were added

Transactions

No records were added

Benefits

No records were added

Additional Classifications

No records were added

Social

No records were added

Metrics & Forecasts

No records were added

Policy

No record was added

Timelines

Asset Life Time

Start Date 2023-04-13
End Date 2073-04-13
Max End Date 2093-04-13

© 2025, Construction Sector Transparency Initiative (CoST Malawi). All Right Reserved;

All content on the platform is licensed under Creative Commons Attribution 4.0 Unported License.