Construction of Karonga DCs Office

Construction of the DCs Office in Karonga District

Provision of office space for the District Commissioner and other officer, since the old office was set on fire.

Start date: 2022-12-22 Due date: 2023-06-10 Approval date: 2022-11-30
99,979,939.00   MWK
Total Funding
2023-04-11
Date Created
2023-06-02
Last updated
Construction
Project Type
Implementation
Project Status
Absence of a clear feasibility study Unrealistic budgets Limited assessment of environmental impacts Limited assessment of social impacts Limited assessment of economic impacts Weak stakeholder engagement Change of scope Cost overruns and budget inflation Lack of transparency in procurement processes Limited competition Favoritism in bidding processes Political interference Weak accountability mechanisms Frequent project delays (time overruns) Environmental violations Social violations Lack of maintenance plans Under-utilization of project Abandonment of project

Locations

Description Located Oposite Karonga cultural Museum
District Karonga
Region Northern
Street address n/a
Postal code

Documents

Title Project Documentation
Description Contract agreement document
Document Type Signed Contract
Date Published 2023-06-02
Date Modified 2023-06-02
Language
Page Start
Page End
Author
Access Details
Title Construction of Karonga DCs Office
Description Current status of The DCs Office
Document Type Annexes to the contract
Date Published 2023-06-02
Date Modified 2023-06-02
Language
Page Start
Page End
Author
Access Details

Parties

Description Karonga District Council
Locality Karonga
Region Northern Region
Street address P.O. Box 35, Karonga
Postal code 0000
Country Malawi
Telephone 00000000
Fax Number n/a
URL n/a
Description Karonga district local government authority.
Description Selemunthu Building Contractors
Locality Karonga
Region North
Street address Karonga
Postal code
Country Malawi
Telephone 0999623869
Fax Number
URL
Description

Contracts

OCID KADC/DDF/W/DC'S-OFC/2020-2021/01
External Reference KADC/DDF/W/DC'S-OFC/2020-2021/01
Title District Commissioner's Office
Description Construction of the District Commissioner's Office in Karonga district
Status Active
Contract Value MWK 99,979,939.25
Cost Estimate MWK 110,000,000.00
Final Value 0.00
Start Date 2022-12-21
End Date 2023-04-10
Max Extent Date 2023-06-30
Duration In Days 191
Procurement Method Open
Method Details Lowest cost
Procuring Entity Karonga District Council-Karonga-MW
Administrative Karonga District Council-Karonga-MW

Documents

No records were added

Modifications

No records were added

Budget

Description Budget breakdown
Amount MWK 99,979,939.25
Start Date 2022-12-21
End Date 2023-04-10
Max Extent Date 2023-06-30
Duration In Days 191
Party ID Karonga District Council-Karonga-MW
URI

Project Funding

Party Karonga District Council-Karonga-MW
Amount MWK 99,979,939.25
Description The project is being funded by District Development Funds
No comments added

Environment

No record was added

Completion

End Date: 2022-12-21
End Details:
Final Scope:
Final Scope Details:
Final Value Amount: 0.00
Final Value Details:

Finances

No records were added

Milestones

No records were added

Transactions

No records were added

Benefits

No records were added

Additional Classifications

No records were added

Social

No records were added

Metrics & Forecasts

No records were added

Policy

No record was added

Timelines

Asset Life Time

Start Date 2022-12-21
End Date 2046-07-20
Max End Date 2063-04-20