Construction of Market Shed at Chitipa Boma

The project will construct a market shed at Chitipa Boma

The project will provide conducive trading place for vendors to ply their trade and reduce roadside accidents due to trading along the streets

Start date: 2022-11-29 Due date: 2023-04-30 Approval date: 2022-11-29
26,931,265.00   MWK
Total Funding
2023-04-11
Date Created
2023-05-30
Last updated
Construction
Project Type
Completion
Project Status
Absence of a clear feasibility study Unrealistic budgets Limited assessment of environmental impacts Limited assessment of social impacts Limited assessment of economic impacts Weak stakeholder engagement Change of scope Cost overruns and budget inflation Lack of transparency in procurement processes Limited competition Favoritism in bidding processes Political interference Weak accountability mechanisms Frequent project delays (time overruns) Environmental violations Social violations Lack of maintenance plans Under-utilization of project Abandonment of project

Locations

Description Construction of Chitipa Boma market shade
District Chitipa
Region Northern
Street address
Postal code

Documents

Title Project Progress Report
Description The report presents the physical progress report as of the date reported.
Document Type Physical progress reports
Date Published 2023-03-17
Date Modified
Language
Page Start
Page End
Author Misheck Gondwe
Access Details
Title Contract
Description Project contract document
Document Type Signed Contract
Date Published
Date Modified
Language
Page Start
Page End
Author
Access Details
Title Picture
Description The completed Boma Market Shed
Document Type Defaults
Date Published
Date Modified
Language
Page Start
Page End
Author
Access Details

Parties

Description Chitipa District Council
Locality Chitipa
Region Northern Region
Street address P.O. Box 1, Chitipa
Postal code 0000
Country Malawi
Telephone 00000000
Fax Number
URL
Description Local government authority for Chitipa district

Contracts

OCID Contract/29/11/22
External Reference
Title Contract
Description The project contract document between Chitipa District Council and Lingstone Construction
Status Closed
Contract Value MWK 26,931,265.00
Cost Estimate MWK 0.00
Final Value 0.00
Start Date 2022-12-06
End Date 2023-03-06
Max Extent Date
Duration In Days 90
Procurement Method Open
Method Details Lowest cost
Procuring Entity Chitipa District Council-Chitipa-MW
Administrative Chitipa District Council-Chitipa-MW

Documents

No records were added

Modifications

No records were added

Budget

Description The Funding is from GESD and it comprises of Substructure 30%, Superstructure and roof 38%, finishing and retention 32%
Amount MWK 26,931,265.00
Start Date 2022-11-29
End Date 2023-03-29
Max Extent Date
Duration In Days 120
Party ID Chitipa District Council-Chitipa-MW
URI

Project Funding

Party National Local Goverment-Lilongwe-MW
Amount MWK 26,931,265.00
Description The project was funded by a performance-based grant -GESD
No comments added

Environment

No record was added

Completion

End Date: 2023-04-30
End Details: Finishing works in progress i.e painting and decoration
Final Scope:
Final Scope Details:
Final Value Amount: MWK 26,931,265.00
Final Value Details:

Finances

No records were added

Milestones

No records were added

Transactions

No records were added

Benefits

No records were added

Additional Classifications

No records were added

Social

No records were added

Metrics & Forecasts

No records were added

Policy

No record was added

Timelines

Asset Life Time

Start Date 2023-04-30
End Date 2063-04-15
Max End Date 2065-04-15

© 2025, Construction Sector Transparency Initiative (CoST Malawi). All Right Reserved;

All content on the platform is licensed under Creative Commons Attribution 4.0 Unported License.