Rehabilitation of Chandawe Health Post- Maternity Wing

The project sought to rehabilitate the maternity wing at Chandawe Health Post

Reduce Mother and Infant mortality rate, through provision of conducive environment for child delivery.

Start date: 2021-12-29 Due date: 2022-03-31 Approval date: 2021-12-01
23,000,000.00   MWK
Total Funding
2023-05-17
Date Created
2023-05-17
Last updated
Rehabilitation
Project Type
Completion
Project Status
Absence of a clear feasibility study Unrealistic budgets Limited assessment of environmental impacts Limited assessment of social impacts Limited assessment of economic impacts Weak stakeholder engagement Change of scope Cost overruns and budget inflation Lack of transparency in procurement processes Limited competition Favoritism in bidding processes Political interference Weak accountability mechanisms Frequent project delays (time overruns) Environmental violations Social violations Lack of maintenance plans Under-utilization of project Abandonment of project

Locations

Description T/A Chilooko
District Ntchisi
Region Central
Street address
Postal code

Documents

Title ESMP for the rehabilitation of Chandawe Health Post
Description The document describes in detail the potential environmental and social impacts associated with the proposed sub project under rehabilitation of Chandawe Health Post and outline mitigation measures required to address the identified impacts
Document Type Environmental Impact
Date Published
Date Modified
Language
Page Start
Page End
Author
Access Details
Title Contract Agreement NS & Marcus Construction- Rehabilitation of Chandawe Health Post- Maternity Wing
Description This is the signed Contract Agreement between Ntchisi District Council and Marcus Construction- Rehabilitation of Chandawe Health Post- Maternity Wing
Document Type Signed Contract
Date Published
Date Modified
Language
Page Start
Page End
Author
Access Details
Title Contract Agreement NS & Marcus Construction- Rehabilitation of Chandawe Health Post- Maternity Wing
Description This is the signed Contract Agreement between Ntchisi District Council and Marcus Construction- Rehabilitation of Chandawe Health Post- Maternity Wing
Document Type Signed Contract
Date Published
Date Modified
Language
Page Start
Page End
Author
Access Details

Parties

No records were added

Contracts

OCID NS/IPDAC/GESD/WKS/2021-22/01-LOT 7
External Reference
Title Contract Agreement Between Ntchisi District Council and Marcus Constructiom
Description The contract states that Marcus Construction is to Executive the rehabilitation of Chandawe Health Post
Status Closed
Contract Value MWK 21,078,462.50
Cost Estimate MWK 23,000,000.00
Final Value 0.00
Start Date 2021-12-29
End Date 2022-03-31
Max Extent Date
Duration In Days 92
Procurement Method Open
Method Details Best proposal
Procuring Entity Ntchisi District Council-Ntchisi-MW
Administrative Ntchisi District Council-Ntchisi-MW

Documents

No records were added

Modifications

No records were added

Budget

Description Approved Budget
Amount MWK 23,000,000.00
Start Date 2021-12-29
End Date 2022-03-31
Max Extent Date
Duration In Days 92
Party ID Ntchisi District Council-Ntchisi-MW
URI
Description Total Project Cost
Amount MWK 25,088,462.00
Start Date 2021-12-29
End Date 2022-03-31
Max Extent Date
Duration In Days 92
Party ID Ntchisi District Council-Ntchisi-MW
URI
Description Expenditure
Amount MWK 24,665,495.09
Start Date 2021-12-29
End Date 2022-03-31
Max Extent Date
Duration In Days 92
Party ID Ntchisi District Council-Ntchisi-MW
URI

Project Funding

Party Ntchisi District Council-Ntchisi-MW
Amount MWK 25,088,462.00
Description This project was funded by the District Development Fund
No comments added

Environment

No record was added

Completion

End Date: 2022-03-31
End Details: Works 100 % done. Ceiling, Plumbing, Wards Demarcation, Rest and Bath Rooms Construction, Drainage Works, Sluice Room Furnishing and Finishing Works done
Final Scope: Health
Final Scope Details:
Final Value Amount: MWK 25,088,462.00
Final Value Details: An addendum of MWK4,010,000 was made

Finances

No records were added

Milestones

No records were added

Transactions

No records were added

Benefits

No records were added

Additional Classifications

No records were added

Social

No records were added

Metrics & Forecasts

No records were added

Policy

No record was added

Timelines

© 2025, Construction Sector Transparency Initiative (CoST Malawi). All Right Reserved;

All content on the platform is licensed under Creative Commons Attribution 4.0 Unported License.