Staff House at Mzandu Health Centre

Construction of One Staff House at Mzandu Health Centre

To increase number of staff accommodation

Start date: 2021-12-29 Due date: 2022-03-31 Approval date: 2021-12-01
29,110,800.00   MWK
Total Funding
2023-05-17
Date Created
2023-05-17
Last updated
Construction
Project Type
Completion
Project Status
Absence of a clear feasibility study Unrealistic budgets Limited assessment of environmental impacts Limited assessment of social impacts Limited assessment of economic impacts Weak stakeholder engagement Change of scope Cost overruns and budget inflation Lack of transparency in procurement processes Limited competition Favoritism in bidding processes Political interference Weak accountability mechanisms Frequent project delays (time overruns) Environmental violations Social violations Lack of maintenance plans Under-utilization of project Abandonment of project

Locations

Description T/A Chikho
District Ntchisi
Region Central
Street address
Postal code

Documents

Title ESMP for construction of Mzandu health post staff house
Description The document describes in detail the potential environmental and social impacts associated with the proposed sub project under construction of staff house at Mzandu health centre and outline mitigation measures required to address the identified impacts.
Document Type Environmental Impact
Date Published
Date Modified
Language
Page Start
Page End
Author
Access Details
Title Contract Agreement- NS & Choice Construction -Staff House at Mzandu Health Centre
Description This is the signed Contract Agreement- between Ntchsi District Council and Choice Construction for the construction of a Staff House at Mzandu Health Centre
Document Type Signed Contract
Date Published
Date Modified
Language
Page Start
Page End
Author
Access Details

Parties

No records were added

Contracts

OCID NS/IPDAC/GESD/WKS/2021-22/01-LOT 2
External Reference
Title Contract Agreement Between Ntchisi District Council and Choice Construction
Description The Contract states that Choice Construction is to execute the construction of staff house at Mzandu Health Centre
Status Closed
Contract Value MWK 29,110,800.00
Cost Estimate MWK 19,000,000.00
Final Value 0.00
Start Date 2021-12-29
End Date 2022-03-31
Max Extent Date
Duration In Days 92
Procurement Method Open
Method Details Best proposal
Procuring Entity Ntchisi District Council-Ntchisi-MW
Administrative Ntchisi District Council-Ntchisi-MW

Documents

No records were added

Modifications

No records were added

Budget

Description Expenditure
Amount MWK 28,194,442.95
Start Date 2021-12-29
End Date 2022-03-31
Max Extent Date
Duration In Days 92
Party ID Ntchisi District Council-Ntchisi-MW
URI
Description Approved Budget
Amount MWK 19,000,000.00
Start Date 2021-12-29
End Date 2022-03-31
Max Extent Date
Duration In Days 92
Party ID Ntchisi District Council-Ntchisi-MW
URI
Description Total Project Cost
Amount MWK 29,110,800.00
Start Date 2021-12-29
End Date 2022-03-31
Max Extent Date
Duration In Days 92
Party ID Ntchisi District Council-Ntchisi-MW
URI

Project Funding

Party Ntchisi District Council-Ntchisi-MW
Amount MWK 29,110,800.00
Description The project was funded by the District Development Fund
No comments added

Environment

No record was added

Completion

End Date: 2022-03-31
End Details: Substructure ,Superstructural Works , Ceiling, Electrification and Plumbing Works done
Final Scope: Health
Final Scope Details:
Final Value Amount: MWK 29,110,800.00
Final Value Details:

Finances

No records were added

Milestones

No records were added

Transactions

No records were added

Benefits

No records were added

Additional Classifications

No records were added

Social

No records were added

Metrics & Forecasts

No records were added

Policy

No record was added

Timelines