Mphanthi Primary school block

construction of a primary school block , furnished with classroom desks and furnished staff room

The project will improve education stands in the district as well as increased enrolment.

Start date: 2023-02-14 Due date: 2023-05-15 Approval date: 2023-02-14
59,951,427.68   MWK
Total Funding
2023-05-17
Date Created
2023-05-17
Last updated
Construction
Project Type
Implementation
Project Status
Absence of a clear feasibility study Unrealistic budgets Limited assessment of environmental impacts Limited assessment of social impacts Limited assessment of economic impacts Weak stakeholder engagement Change of scope Cost overruns and budget inflation Lack of transparency in procurement processes Limited competition Favoritism in bidding processes Political interference Weak accountability mechanisms Frequent project delays (time overruns) Environmental violations Social violations Lack of maintenance plans Under-utilization of project Abandonment of project

Locations

Description MPHANTHI SCHOOL BLOCKPROJECT LOCATION
District Dedza
Region Central
Street address N/A
Postal code 140

Documents

No records were added

Parties

Description Dedza District Council
Locality Dedza
Region Central Region
Street address Shire HN# 137
Postal code P.O. Box 2882
Country Malawi
Telephone +265999299777
Fax Number
URL
Description
Description South gate construction
Locality Lilongwe
Region
Street address Lilongwe
Postal code
Country Malawi
Email @gmail.com
Telephone 0000
Fax Number
URL
Description

Contracts

OCID N/A
External Reference N/A
Title MPHANTHI SCHOOL BLOCK CONTRACT DETAILS
Description Contract for Construction of Classroom Blockb at Mphanthi Primary School
Status Active
Contract Value MWK 59,951,428.00
Cost Estimate MWK 59,951,428.00
Final Value 0.00
Start Date 2023-02-13
End Date 2023-05-14
Max Extent Date 2023-05-21
Duration In Days 97
Procurement Method Open
Method Details Best value to government
Procuring Entity South gate construction-Lilongwe-MW
Administrative Dedza District Council-Dedza-MW

Documents

No records were added

Modifications

No records were added

Budget

Description MPHANTHI SCHOOL BLOCK BUDGET BREAKDOWN
Amount MWK 59,951,428.00
Start Date 2023-02-13
End Date 2023-05-14
Max Extent Date 2023-05-21
Duration In Days 97
Party ID Dedza District Council-Dedza-MW
URI

Project Funding

Party Dedza District Council-Dedza-MW
Amount MWK 59,951,428.00
Description CONTRACT AMOUNT FUNDED BY GESD PBG
No comments added

Environment

No record was added

Completion

End Date:
End Details:
Final Scope:
Final Scope Details:
Final Value Amount: 0.00
Final Value Details:

Finances

No records were added

Milestones

No records were added

Transactions

No records were added

Benefits

No records were added

Additional Classifications

No records were added

Social

No records were added

Metrics & Forecasts

No records were added

Policy

No record was added

Timelines

Asset Life Time

Start Date 2023-02-14
End Date 2043-02-15
Max End Date 2043-02-15

© 2025, Construction Sector Transparency Initiative (CoST Malawi). All Right Reserved;

All content on the platform is licensed under Creative Commons Attribution 4.0 Unported License.