Construction of Primary Schools and Rehabilitation of Education facilities

Return
image

Construction of Primary Schools and Rehabilitation of Education facilities

Construction of 14 Urban Primary Schools in Blantyre, Lilongwe, Mzuzu and Zomba

To decongest some of the highly populated urban primary schools

Start date: 2018-07-01 Due date: 2024-03-31 Approval date: 2018-07-01
10,000,000,000.00   MWK
Total Funding
2023-05-17
Date Created
2023-05-17
Last updated
Construction
Project Type
Implementation
Project Status
Absence of a clear feasibility study Unrealistic budgets Limited assessment of environmental impacts Limited assessment of social impacts Limited assessment of economic impacts Weak stakeholder engagement Change of scope Cost overruns and budget inflation Lack of transparency in procurement processes Limited competition Favoritism in bidding processes Political interference Weak accountability mechanisms Frequent project delays (time overruns) Environmental violations Social violations Lack of maintenance plans Under-utilization of project Abandonment of project

Locations

No records were added

Documents

No records were added

Parties

No records were added

Contracts

OCID 025/IPC/MOEST/EIMU/PS/CIT/2018-4B
External Reference
Title Construction of BCA Hill Primary School in Blantyre
Description Construction of 8no. classroom blocks, 1no. administration block, 2no. staff houses, pit latrines, urinals and associated external works.
Status Active
Contract Value MWK 392,420,552.00
Cost Estimate MWK 0.00
Final Value 0.00
Start Date 2018-07-01
End Date 2019-06-30
Max Extent Date 2024-03-31
Duration In Days 2100
Procurement Method Open
Method Details Best value to government
Procuring Entity Ministry of Education-Lilongwe-MW
Administrative Ministry of Education-Lilongwe-MW

Documents

No records were added

Modifications

No records were added
OCID 025/IPC/MOEST/EIMU/PS/CIT/2018-3B
External Reference
Title Construction of Namalowe Primary School in Blantyre
Description Construction of 8no. classroom blocks, 1no. administration block, 2no. staff houses, pit latrines, urinals and associated external works.
Status Active
Contract Value MWK 380,722,243.00
Cost Estimate MWK 0.00
Final Value 0.00
Start Date 2018-07-01
End Date 2019-06-30
Max Extent Date 2024-03-31
Duration In Days 2100
Procurement Method Open
Method Details Best value to government
Procuring Entity Ministry of Education-Lilongwe-MW
Administrative Ministry of Education-Lilongwe-MW

Documents

No records were added

Modifications

No records were added
OCID 025/IPC/MOEST/EIMU/PS/CIT/2018-5B
External Reference
Title Construction of Mbayani Primary School in Blantyre
Description Construction of 8no. classroom blocks, 1no. administration block, 2no. staff houses, pit latrines, urinals and associated external works.
Status Active
Contract Value MWK 456,956,275.70
Cost Estimate MWK 0.00
Final Value 0.00
Start Date 2018-07-01
End Date 2019-06-30
Max Extent Date
Duration In Days 364
Procurement Method Open
Method Details Best value to government
Procuring Entity Ministry of Education-Lilongwe-MW
Administrative Ministry of Education-Lilongwe-MW

Documents

No records were added

Modifications

No records were added
OCID 025/IPC/MOEST/EIMU/PS/CIT/2018-1B
External Reference
Title Construction of Chapima Heights Primary School in Blantyre
Description Construction of 8no. classroom blocks, 1no. administration block, 2no. staff houses, pit latrines, urinals and associated external works.
Status Active
Contract Value MWK 420,759,822.70
Cost Estimate MWK 0.00
Final Value 0.00
Start Date 2018-07-01
End Date 2019-06-30
Max Extent Date 2024-03-31
Duration In Days 2100
Procurement Method Open
Method Details Best value to government
Procuring Entity Ministry of Education-Lilongwe-MW
Administrative Ministry of Education-Lilongwe-MW

Documents

No records were added

Modifications

No records were added
OCID 025/IPC/MOEST/EIMU/PS/CIT/2018-2B
External Reference
Title Construction of Mzedi Primary School in Blantyre
Description Construction of 8no. classroom blocks, 1no. administration block, 2no. staff houses, pit latrines, urinals and associated external works.
Status Pre-award
Contract Value MWK 10.00
Cost Estimate MWK 0.00
Final Value 0.00
Start Date 2023-05-17
End Date 2023-05-17
Max Extent Date 2023-05-18
Duration In Days 1
Procurement Method Open
Method Details Best value to government
Procuring Entity Ministry of Education-Lilongwe-MW
Administrative Ministry of Education-Lilongwe-MW

Documents

No records were added

Modifications

No records were added
OCID 025/IPC/MOEST/EIMU/PS/CIT/2018-14B
External Reference
Title Construction of Chayamba Primary School in Lilongwe
Description Construction of 8no. classroom blocks, 1no. administration block, 2no. staff houses, pit latrines, urinals and associated external works.
Status Active
Contract Value MWK 436,363,747.95
Cost Estimate MWK 0.00
Final Value 0.00
Start Date 2018-07-01
End Date 2019-06-30
Max Extent Date 2024-03-31
Duration In Days 2100
Procurement Method Open
Method Details Best value to government
Procuring Entity Ministry of Education-Lilongwe-MW
Administrative Ministry of Education-Lilongwe-MW

Documents

No records were added

Modifications

No records were added
OCID 025/IPC/MOEST/EIMU/PS/CIT/2018-10B
External Reference
Title Construction of Chidzingwe Primary School in Lilongwe
Description Construction of 8no. classroom blocks, 1no. administration block, 2no. staff houses, pit latrines, urinals and associated external works.
Status Active
Contract Value MWK 398,524,181.00
Cost Estimate MWK 0.00
Final Value 0.00
Start Date 2018-07-01
End Date 2019-06-30
Max Extent Date 2024-03-31
Duration In Days 2100
Procurement Method Open
Method Details Best value to government
Procuring Entity Ministry of Education-Lilongwe-MW
Administrative Ministry of Education-Lilongwe-MW

Documents

No records were added

Modifications

No records were added
OCID 025/IPC/MOEST/EIMU/PS/CIT/2018-6B
External Reference
Title Construction of Ching'ombe Primary School in Lilongwe
Description Construction of 8no. classroom blocks, 1no. administration block, 2no. staff houses, pit latrines, urinals and associated external works.
Status Active
Contract Value MWK 427,755,317.26
Cost Estimate MWK 0.00
Final Value 0.00
Start Date 2018-07-01
End Date 2019-06-30
Max Extent Date 2024-03-31
Duration In Days 2100
Procurement Method Open
Method Details Best value to government
Procuring Entity Ministry of Education-Lilongwe-MW
Administrative Ministry of Education-Lilongwe-MW

Documents

No records were added

Modifications

No records were added
OCID 025/IPC/MOEST/EIMU/PS/CIT/111/2018-11A
External Reference
Title Construction of Bwemba Primary School in Lilongwe
Description Construction of 8no. classroom blocks, 1no. administration block, 2no. staff houses, pit latrines, urinals and associated external works.
Status Closed
Contract Value MWK 429,022,283.25
Cost Estimate MWK 0.00
Final Value 0.00
Start Date 2018-07-01
End Date 2019-06-30
Max Extent Date 2023-01-01
Duration In Days 1645
Procurement Method Open
Method Details Best value to government
Procuring Entity Ministry of Education-Lilongwe-MW
Administrative Ministry of Education-Lilongwe-MW

Documents

No records were added

Modifications

No records were added
OCID 025/IPC/MOEST/EIMU/PS/CIT/111/2018-8A
External Reference
Title Construction of Mgona Primary School in Lilongwe
Description Construction of 8no. classroom blocks, 1no. administration block, 2no. staff houses, pit latrines, urinals and associated external works.
Status Active
Contract Value MWK 433,337,488.36
Cost Estimate 0.00
Final Value 0.00
Start Date 2018-07-01
End Date 2019-06-30
Max Extent Date 2024-03-31
Duration In Days 2100
Procurement Method Open
Method Details Best value to government
Procuring Entity Ministry of Education-Lilongwe-MW
Administrative Ministry of Education-Lilongwe-MW

Documents

No records were added

Modifications

No records were added
OCID 025/IPC/MOEST/EIMU/PS/CIT/2018-10B
External Reference
Title Construction of Chiludede Primary School in Mzuzu
Description Construction of 8no. classroom blocks, 1no. administration block, 2no. staff houses, pit latrines, urinals and associated external works.
Status Active
Contract Value MWK 459,929,145.50
Cost Estimate MWK 0.00
Final Value 0.00
Start Date 2018-07-01
End Date 2019-06-30
Max Extent Date 2024-03-31
Duration In Days 2100
Procurement Method Open
Method Details Best value to government
Procuring Entity Ministry of Education-Lilongwe-MW
Administrative Ministry of Education-Lilongwe-MW

Documents

No records were added

Modifications

No records were added
OCID 025/IPC/MOEST/EIMU/PS/CIT/2018-14B
External Reference
Title Construction of Mzilawayingwe Primary School in Mzuzu
Description Construction of 8no. classroom blocks, 1no. administration block, 2no. staff houses, pit latrines, urinals and associated external works.
Status Active
Contract Value MWK 677,673,097.11
Cost Estimate MWK 0.00
Final Value 0.00
Start Date 2018-07-01
End Date 2019-06-30
Max Extent Date 2024-03-31
Duration In Days 2100
Procurement Method Open
Method Details Best value to government
Procuring Entity Ministry of Education-Lilongwe-MW
Administrative Ministry of Education-Lilongwe-MW

Documents

No records were added

Modifications

No records were added
OCID 025/IPC/MOEST/EIMU/PS/CIT/2018-13
External Reference
Title Construction of Chinamwali Primary School in Lilongwe
Description Construction of 8no. classroom blocks, 1no. administration block, 2no. staff houses, pit latrines, urinals and associated external works.
Status Active
Contract Value MWK 411,482,696.80
Cost Estimate MWK 0.00
Final Value 0.00
Start Date 2018-07-01
End Date 2019-06-30
Max Extent Date 2024-03-31
Duration In Days 2100
Procurement Method Open
Method Details Best value to government
Procuring Entity Ministry of Education-Lilongwe-MW
Administrative Ministry of Education-Lilongwe-MW

Documents

No records were added

Modifications

No records were added
OCID 025/IPC/MOEST/EIMU/PS/CIT/2018-7B
External Reference
Title Construction of Mtiya Primary School in Zomba
Description Construction of 8no. classroom blocks, 1no. administration block, 2no. staff houses, pit latrines, urinals and associated external works.
Status Active
Contract Value MWK 355,594,415.54
Cost Estimate MWK 0.00
Final Value 0.00
Start Date 2018-07-01
End Date 2019-06-30
Max Extent Date 2024-03-31
Duration In Days 2100
Procurement Method Open
Method Details Best value to government
Procuring Entity Ministry of Education-Lilongwe-MW
Administrative Ministry of Education-Lilongwe-MW

Documents

No records were added

Modifications

No records were added

Budget

No records were added

Project Funding

No records were added
No comments added

Environment

No record was added

Completion

End Date:
End Details:
Final Scope:
Final Scope Details:
Final Value Amount: 0.00
Final Value Details:

Finances

No records were added

Milestones

No records were added

Transactions

No records were added

Benefits

No records were added

Additional Classifications

No records were added

Social

No records were added

Metrics & Forecasts

No records were added

Policy

No record was added

Timelines

Asset Life Time

Start Date 2024-03-31
End Date 2074-03-31
Max End Date 2074-03-31

© 2025, Construction Sector Transparency Initiative (CoST Malawi). All Right Reserved;

All content on the platform is licensed under Creative Commons Attribution 4.0 Unported License.