INSTALLATION OF CULVERT RINGS AND RIVER CHANNELLING AT CHIMBUNA WARD

Return
image

INSTALLATION OF CULVERT RINGS AND RIVER CHANNELLING AT CHIMBUNA WARD

The project involved excavation works concrete works, masonry works, plastering, backfilling

To improve accessibility and drainage systems

Start date: 2022-07-06 Due date: 2024-03-31 Approval date: 2022-07-01
1,000,000.00   MWK
Total Funding
2023-05-19
Date Created
2023-06-19
Last updated
Construction
Project Type
Completion
Project Status
Absence of a clear feasibility study Unrealistic budgets Limited assessment of environmental impacts Limited assessment of social impacts Limited assessment of economic impacts Weak stakeholder engagement Change of scope Cost overruns and budget inflation Lack of transparency in procurement processes Limited competition Favoritism in bidding processes Political interference Weak accountability mechanisms Frequent project delays (time overruns) Environmental violations Social violations Lack of maintenance plans Under-utilization of project Abandonment of project

Locations

Description The project is located close to community police room
District Kasungu
Region Central
Street address
Postal code 201310

Documents

No records were added

Parties

Description Kasungu Municipal Council
Locality Kasungu
Region Central Region
Street address Kasungu
Postal code 0000
Country Malawi
Telephone +2659900000
Fax Number
URL
Description

Contracts

No records were added

Budget

Description INSTALLATION OF CULVERT RINGS AND RIVER CHANNELLING
Amount MWK 1,000,000.00
Start Date 2022-07-06
End Date 2024-03-31
Max Extent Date 2024-03-31
Duration In Days 634
Party ID Kasungu Municipal Council-Kasungu-MW
URI

Project Funding

Party Kasungu Municipal Council-Kasungu-MW
Amount MWK 1,000,000.00
Description
No comments added

Environment

No record was added

Completion

End Date: 2023-03-31
End Details:
Final Scope:
Final Scope Details:
Final Value Amount: 0.00
Final Value Details:

Finances

No records were added

Milestones

No records were added

Transactions

No records were added

Benefits

No records were added

Additional Classifications

No records were added

Social

No records were added

Metrics & Forecasts

No records were added

Policy

No record was added

Timelines

Asset Life Time

Start Date 2024-03-31
End Date 2034-03-31
Max End Date 2034-03-31

© 2025, Construction Sector Transparency Initiative (CoST Malawi). All Right Reserved;

All content on the platform is licensed under Creative Commons Attribution 4.0 Unported License.