Project

Multinational Nacala Road Corridor Development Project Phase V: Feasibility Study, Detailed Engineering Design for the Rehabilitation of Mangochi - Chiponde Road

Return
image

Multinational Nacala Road Corridor Development Project Phase V: Feasibility Study, Detailed Engineering Design for the Rehabilitation of Mangochi - Chiponde Road

Design for the Rehabilitation of Mangochi - Chiponde Road

The development and growth of the economy

Start date: 2022-08-18 Due date: 2023-06-07 Approval date: 2022-03-31
421,506.50   USD
Total Funding
2023-06-01
Date Created
2023-06-01
Last updated
Rehabilitation
Project Type
Implementation
Project Status
Absence of a clear feasibility study Unrealistic budgets Limited assessment of environmental impacts Limited assessment of social impacts Limited assessment of economic impacts Weak stakeholder engagement Change of scope Cost overruns and budget inflation Lack of transparency in procurement processes Limited competition Favoritism in bidding processes Political interference Weak accountability mechanisms Frequent project delays (time overruns) Environmental violations Social violations Lack of maintenance plans Under-utilization of project Abandonment of project

Locations

Description Feasibility Study, Detailed Engineering Design for the Rehabilitation of Mangochi - Chiponde Road
District Mangochi
Region Southern
Street address
Postal code

Documents

No records were added

Parties

Description African Development Bank Group (AfDB)
Locality Abidjan
Region Abidjan
Street address African Development Bank Group Avenue Joseph Anoma 01 BP 1387 Abidjan 01 Côte d'Ivoire
Postal code 01 BP 1387
Country Ivory Coast
Telephone +225 27 2026 3900
Fax Number
URL 0000
Description The overarching objective of the African Development Bank (AfDB) Group is to spur sustainable economic development and social progress in its regional member countries (RMCs), thus contributing to poverty reduction. The Bank Group achieves this objective by: mobilizing and allocating resources for investment in RMCs; and providing policy advice and technical assistance to support development efforts. In 2015, all multilateral development institutions have agreed on a same set of objectives, called the Sustainable Development Goals.

Contracts

OCID RA/CON/2019-20/02
External Reference
Title Feasibility Study, Detailed Engineering Design for the Rehabilitation of Mangochi - Chiponde Road
Description Group Consulta Global (PTY) Limited (Botswana)
Status Active
Contract Value USD 421,506.50
Cost Estimate USD 421,506.50
Final Value 0.00
Start Date 2022-08-18
End Date 2023-06-07
Max Extent Date
Duration In Days 293
Procurement Method Open
Method Details Best value to government
Procuring Entity Roads Authority-Lilongwe-MW
Administrative Roads Authority-Lilongwe-MW

Documents

No records were added

Modifications

No records were added

Budget

No records were added

Project Funding

Party African Development Bank Group (AfDB)-Abidjan-CI
Amount USD 421,506.50
Description Feasibility Study, Detailed Engineering Design for the Rehabilitation of Mangochi - Chiponde Road
No comments added

Environment

No record was added

Completion

End Date:
End Details:
Final Scope:
Final Scope Details:
Final Value Amount: 0.00
Final Value Details:

Finances

No records were added

Milestones

No records were added

Transactions

No records were added

Benefits

No records were added

Additional Classifications

No records were added

Social

No records were added

Metrics & Forecasts

No records were added

Policy

No record was added

Timelines