image

CONSTRUCTION OF A GATEWAY ADMINISTRATION BLOCK

The main aim of the project is to Construct the Offices for the LUANAR

The offices are to be used by the University offices

Start date: 2013-08-01 Due date: 2022-08-26 Approval date: 2022-08-10
100,000,000.00   MWK
Total Funding
2022-08-12
Date Created
2022-08-12
Last updated
Construction
Project Type
Implementation
Project Status
Absence of a clear feasibility study Unrealistic budgets Limited assessment of environmental impacts Limited assessment of social impacts Limited assessment of economic impacts Weak stakeholder engagement Change of scope Cost overruns and budget inflation Lack of transparency in procurement processes Limited competition Favoritism in bidding processes Political interference Weak accountability mechanisms Frequent project delays (time overruns) Environmental violations Social violations Lack of maintenance plans Under-utilization of project Abandonment of project

Locations

No records were added

Documents

No records were added

Parties

Description Lilongwe University of Agriculture and Natural Resources
Locality Lilongwe
Region Central Region
Street address Post Office Box 219, Lilongwe
Postal code 0000
Country Malawi
Telephone +(265) 01 277 222/260
Fax Number
URL https://www.luanar.ac.mw
Description A public University
Description Terrastone Construction Limited
Locality Lilongwe
Region Central
Street address P.O Box 995,Lilongwe
Postal code
Country Malawi
Telephone 0888 829 227
Fax Number
URL
Description Local Permanent Building Unlimited

Contracts

OCID GAB
External Reference GAB
Title construction of Gateway Administration Block
Description construction of an administration block
Status Active
Contract Value MWK 100,000,000.00
Cost Estimate MWK 100,000,000.00
Final Value 0.00
Start Date 2022-08-12
End Date 2026-08-07
Max Extent Date 2026-11-05
Duration In Days 1546
Procurement Method Open
Method Details Best value to government
Procuring Entity Lilongwe University of Agriculture and Natural Resources-Lilongwe-MW
Administrative Lilongwe University of Agriculture and Natural Resources-Lilongwe-MW

Documents

No records were added

Modifications

No records were added

Budget

Description Construction of Gateway Administration Block
Amount MWK 100,000,000.00
Start Date 2022-08-12
End Date 2022-08-26
Max Extent Date
Duration In Days 14
Party ID Terrastone Construction Limited-Lilongwe-MW
URI

Project Funding

No records were added
No comments added

Environment

No record was added

Completion

End Date:
End Details:
Final Scope:
Final Scope Details:
Final Value Amount: 0.00
Final Value Details:

Finances

No records were added

Milestones

No records were added

Transactions

No records were added

Benefits

No records were added

Additional Classifications

No records were added

Social

No records were added

Metrics & Forecasts

No records were added

Policy

No record was added

Timelines

Asset Life Time

Start Date 2022-08-12
End Date 2032-11-25
Max End Date 2022-08-19

© 2025, Construction Sector Transparency Initiative (CoST Malawi). All Right Reserved;

All content on the platform is licensed under Creative Commons Attribution 4.0 Unported License.