image

Construction of Boma Shops

Constructing 5 shops and completing toilet block that was at window level.

Revenue generation for the council

Start date: 2023-01-18 Due date: 2023-05-18 Approval date: 2023-05-09
60,699,999.76   MWK
Total Funding
2023-09-06
Date Created
2023-09-06
Last updated
Construction
Project Type
Completion
Project Status
Absence of a clear feasibility study Unrealistic budgets Limited assessment of environmental impacts Limited assessment of social impacts Limited assessment of economic impacts Weak stakeholder engagement Change of scope Cost overruns and budget inflation Lack of transparency in procurement processes Limited competition Favoritism in bidding processes Political interference Weak accountability mechanisms Frequent project delays (time overruns) Environmental violations Social violations Lack of maintenance plans Under-utilization of project Abandonment of project

Locations

Description TA Kanduku, GVH Mchotseni
District Mwanza
Region Southern
Street address
Postal code

Documents

Title Contract Agreement for Boma shops
Description Signed contract for Construction of Boma shops
Document Type Signed Contract
Date Published
Date Modified
Language
Page Start
Page End
Author
Access Details

Parties

Description Mwanza District Council
Locality Mwanza
Region
Street address Mwanza
Postal code
Country Malawi
Email @gmail.com
Telephone 000
Fax Number
URL
Description
Description Fidelis Building Contractors
Locality Zomba
Region Southern Region
Street address P.O. Box 330, Zomba
Postal code 0000
Country Malawi
Email 0000
Telephone 0000
Fax Number
URL 0000
Description A registered building contractor with NCIC under the unlimited categoy

Contracts

OCID MW-MDC 318973-CW-RFQ
External Reference
Title Construction of shops
Description Signed contract
Status Active
Contract Value MWK 60,699,999.76
Cost Estimate MWK 60,699,999.76
Final Value 0.00
Start Date 2023-01-18
End Date 2023-05-18
Max Extent Date
Duration In Days 120
Procurement Method Open
Method Details Rated criteria
Procuring Entity Mwanza District Council-Mwanza-MW
Administrative Mwanza District Council-Mwanza-MW

Documents

No records were added

Modifications

No records were added
OCID MW-MDC 318973-CW-RFQ
External Reference
Title Construction of shops
Description Signed contract
Status Active
Contract Value MWK 60,699,999.76
Cost Estimate MWK 60,699,999.76
Final Value 0.00
Start Date 2023-01-18
End Date 2023-05-18
Max Extent Date
Duration In Days 120
Procurement Method Open
Method Details Rated criteria
Procuring Entity Mwanza District Council-Mwanza-MW
Administrative Mwanza District Council-Mwanza-MW

Documents

No records were added

Modifications

No records were added
OCID MW-MDC 318973-CW-RFQ
External Reference
Title Construction of shops
Description Signed contract
Status Active
Contract Value MWK 60,699,999.76
Cost Estimate MWK 60,699,999.76
Final Value 0.00
Start Date 2023-01-18
End Date 2023-05-18
Max Extent Date
Duration In Days 120
Procurement Method Open
Method Details Rated criteria
Procuring Entity Mwanza District Council-Mwanza-MW
Administrative Mwanza District Council-Mwanza-MW

Documents

No records were added

Modifications

No records were added

Budget

Description Contract Reference Number
Amount MWK 60,699,999.76
Start Date 2023-01-18
End Date 2023-05-18
Max Extent Date
Duration In Days 120
Party ID Mwanza District Council-Mwanza-MW
URI

Project Funding

Party World Bank-Washington, DC-US
Amount MWK 60,699,999.76
Description Funded though GESD
No comments added

Environment

No record was added

Completion

End Date: 2023-06-30
End Details: Completed
Final Scope: Completed
Final Scope Details: Completed. Awaiting handover
Final Value Amount: MWK 60,652,069.18
Final Value Details: Within contract amount

Finances

No records were added

Milestones

No records were added

Transactions

No records were added

Benefits

No records were added

Additional Classifications

No records were added

Social

No records were added

Metrics & Forecasts

No records were added

Policy

No record was added

Timelines

Asset Life Time

Start Date 2023-06-30
End Date
Max End Date

© 2025, Construction Sector Transparency Initiative (CoST Malawi). All Right Reserved;

All content on the platform is licensed under Creative Commons Attribution 4.0 Unported License.