Development of a Robust Standardization, Quality Assurance, Accreditation and Metrology (SQAM) Infrastructure in Malawi
Construction of Office and Laboratory Complex
To build capacity in regulating requirements of the Malawi Bureau of Standards (MBS) by improving testing requirements and thereby contribute to the improvement of export trade, economic improvement and welfare of Malawians
Start date: 2016-02-01
Due date:
2022-09-30
Approval date: 2014-07-01
Absence of a clear feasibility study
Unrealistic budgets
Limited assessment of environmental impacts
Limited assessment of social impacts
Limited assessment of economic impacts
Weak stakeholder engagement
Change of scope
Cost overruns and budget inflation
Lack of transparency in procurement processes
Limited competition
Favoritism in bidding processes
Political interference
Weak accountability mechanisms
Frequent project delays (time overruns)
Environmental violations
Social violations
Lack of maintenance plans
Under-utilization of project
Abandonment of project
Description
The Malawi Bureau of Standards (MBS) is a statutory organization established in 1972 by an Act of Parliament (Cap 51:02) of the Laws of Malawi (Amended as Act No 14 of 2012), with a mandate to promote metrology, standardization and quality assurance of commodities and of the manufacture, production, processing or treatment thereof; and further to provide for matters incidental to, or connected with standardization. The MBS is governed by a Board of Directors, the MBS Board, which is appointed by Government. It is responsible for managing the operations of the MBS.
Contracts
OCID
n/a
External Reference
Title
Design and Supervision
Description
Project Design and Supervision
Status
Active
Contract Value
MWK 413,812,900.00
Cost Estimate
MWK 413,812,900.00
Final Value
0.00
Start Date
2016-02-01
End Date
2018-01-31
Max Extent Date
2022-09-30
Duration In Days
2433
Procurement Method
Open
Method Details
Best value to government
Procuring Entity
Malawi Bureau of Standards (MBS)-Blantyre-MW
Administrative
Directorate of Buildings (DoB)-Lilongwe-MW
Documents
No records were added
Modifications
No records were added
OCID
SQAM
External Reference
Title
Construction
Description
Construction of Laboratory and Office Complex
Status
Active
Contract Value
MWK 18,276,239,599.70
Cost Estimate
18,276,239,599.70
Final Value
0.00
Start Date
2016-02-01
End Date
2018-01-31
Max Extent Date
2022-09-30
Duration In Days
2433
Procurement Method
Open
Method Details
Best value to government
Procuring Entity
Malawi Bureau of Standards (MBS)-Blantyre-MW
Administrative
Directorate of Buildings (DoB)-Lilongwe-MW
Documents
No records were added
Modifications
No records were added
OCID
SQAM
External Reference
Title
Construction
Description
Construction of Laboratory and Office Complex
Status
Active
Contract Value
MWK 18,276,239,599.70
Cost Estimate
18,276,239,599.70
Final Value
0.00
Start Date
2016-02-01
End Date
2018-01-31
Max Extent Date
2022-09-30
Duration In Days
2433
Procurement Method
Open
Method Details
Best value to government
Procuring Entity
Malawi Bureau of Standards (MBS)-Blantyre-MW
Administrative
Directorate of Buildings (DoB)-Lilongwe-MW
Documents
No records were added
Modifications
No records were added
OCID
SQAM
External Reference
Title
Construction
Description
Construction of Laboratory and Office Complex
Status
Active
Contract Value
MWK 18,276,239,599.70
Cost Estimate
MWK 18,276,239,600.00
Final Value
0.00
Start Date
2016-02-01
End Date
2018-01-31
Max Extent Date
2022-09-30
Duration In Days
2433
Procurement Method
Open
Method Details
Best value to government
Procuring Entity
Malawi Bureau of Standards (MBS)-Blantyre-MW
Administrative
Directorate of Buildings (DoB)-Lilongwe-MW
Documents
No records were added
Modifications
No records were added
Budget
Description
Budgets for the building contractor based on Certificates of Completion
Amount
MWK 18,276,239,600.00
Start Date
2016-02-01
End Date
2022-09-30
Max Extent Date
2024-09-30
Duration In Days
3164
Party ID
Malawi Government-Lilongwe-MW
URI
Description
Design and Supervision
Amount
MWK 413,812,900.00
Start Date
2015-07-01
End Date
2022-09-30
Max Extent Date
2024-09-30
Duration In Days
3379
Party ID
Malawi Bureau of Standards (MBS)-Blantyre-MW