Project

Construction of Waluma CDSS School Block 2 and furnishing it with students desks and teachers chairs and desks

Return
image

Construction of Waluma CDSS School Block 2 and furnishing it with students desks and teachers chairs and desks

The project will involve the Construction of Waluma School block 2 and furnishing it with Desks

To ease access to education to learners within the surrounding community.

Start date: 2022-11-07 Due date: 2023-02-05 Approval date: 2022-11-28
58,940,486.46   MWK
Total Funding
2023-09-06
Date Created
2023-09-06
Last updated
Construction
Project Type
Completion
Project Status
Absence of a clear feasibility study Unrealistic budgets Limited assessment of environmental impacts Limited assessment of social impacts Limited assessment of economic impacts Weak stakeholder engagement Change of scope Cost overruns and budget inflation Lack of transparency in procurement processes Limited competition Favoritism in bidding processes Political interference Weak accountability mechanisms Frequent project delays (time overruns) Environmental violations Social violations Lack of maintenance plans Under-utilization of project Abandonment of project

Locations

No records were added

Documents

No records were added

Parties

No records were added

Contracts

No records were added

Budget

No records were added

Project Funding

No records were added
No comments added

Environment

No record was added

Completion

End Date: 2023-01-31
End Details: The project is almost 95% completion
Final Scope: 1 classroom block constructed and 120 desks will be provided
Final Scope Details: 1 classroom block constructed and 120 desks will be provided
Final Value Amount: MWK 58,940,486.46
Final Value Details: Fifty eight million nine hundred and forty thousand four hundred eighty six kwacha forty six tambala

Finances

No records were added

Milestones

No records were added

Transactions

No records were added

Benefits

No records were added

Additional Classifications

No records were added

Social

No records were added

Metrics & Forecasts

No records were added

Policy

No record was added

Timelines

Asset Life Time

Start Date 2022-11-07
End Date 2023-02-08
Max End Date 2023-09-06