CHIMATIRO MATERNITY WING

CONSTRUCTION OF CHIMATIRO MATERNITY WING, SEPTIC TANK, PLACENTA PIT AND WATER TANK

IMPROVING ACCESS TO MATERNAL HEALTH

Start date: 2021-12-13 Due date: 2022-09-30 Approval date: 2021-11-29
44,155,453.17   MWK
Total Funding
2022-08-17
Date Created
2023-09-06
Last updated
Construction
Project Type
Completion
Project Status
Absence of a clear feasibility study Unrealistic budgets Limited assessment of environmental impacts Limited assessment of social impacts Limited assessment of economic impacts Weak stakeholder engagement Change of scope Cost overruns and budget inflation Lack of transparency in procurement processes Limited competition Favoritism in bidding processes Political interference Weak accountability mechanisms Frequent project delays (time overruns) Environmental violations Social violations Lack of maintenance plans Under-utilization of project Abandonment of project

Locations

Description TA SAWALI/CHIMATIRO VDC/ NEAR SAWALI TRADING CENTRE/NKHONDE WARD/ BALAK CENTRAL EAST
District Balaka
Region Southern
Street address SAWALI TRADING CENTRE
Postal code 1

Documents

No records were added

Parties

Description Balaka District Council
Locality Balaka
Region South
Street address off balaka main road next to Meru filling station
Postal code P/Bag 1
Country Malawi
Telephone 265 1 552 049
Fax Number 265 1 552 050/790
URL http://balakadistrictcouncil.com
Description Description
Description Mathews Phiri Civil Engineering
Locality Zomba
Region Southern Region
Street address P.O. Box 314, Zomba
Postal code 0000
Country Malawi
Email 0000
Telephone +265995219619
Fax Number
URL 0000
Description A registered Civil contractor in the K50.0 million category.

Contracts

No records were added

Budget

Description CHIMATIRO MATERNITY WING
Amount MWK 44,155,453.17
Start Date 2021-12-13
End Date 2022-04-30
Max Extent Date 2022-09-30
Duration In Days 291
Party ID Balaka District Council-Balaka-MW
URI WWWW.balakadc.com

Project Funding

No records were added
No comments added

Environment

No record was added

Completion

End Date: 2023-09-01
End Details: The project was completed within the implementation period
Final Scope: Completed with additional External works
Final Scope Details: Main clinic block, placenta pit, ash pit, incinerator
Final Value Amount: MWK 67,344,480.52
Final Value Details: completed with additional cost

Finances

No records were added

Milestones

No records were added

Transactions

No records were added

Benefits

No records were added

Additional Classifications

No records were added

Social

No records were added

Metrics & Forecasts

No records were added

Policy

No record was added

Timelines

Asset Life Time

Start Date 2022-10-03
End Date 2052-12-27
Max End Date 2062-08-25

© 2025, Construction Sector Transparency Initiative (CoST Malawi). All Right Reserved;

All content on the platform is licensed under Creative Commons Attribution 4.0 Unported License.