Malawi Energy Power Restoration Project: Kapichira Dam Rehabilitation and Strengthening

Return
image

Malawi Energy Power Restoration Project: Kapichira Dam Rehabilitation and Strengthening

Malawi Energy Restoration Project is an emergency project that is aimed at rehabilitating the Kapichira dam to enable power generation. The Malawi Government with loan of $44.4 million from the World Bank intents to implement this project as a matter of emergency.

The project aims to restore power generation at Kapichira Powerstation. Kapichira Dam was destroyed by Cycle Ana during the January 2022 floods

Start date: 2022-07-01 Due date: 2027-06-16 Approval date: 2022-07-20
44,400,000.00   USD
Total Funding
2022-08-17
Date Created
2023-09-06
Last updated
Rehabilitation
Project Type
Implementation
Project Status
Absence of a clear feasibility study Unrealistic budgets Limited assessment of environmental impacts Limited assessment of social impacts Limited assessment of economic impacts Weak stakeholder engagement Change of scope Cost overruns and budget inflation Lack of transparency in procurement processes Limited competition Favoritism in bidding processes Political interference Weak accountability mechanisms Frequent project delays (time overruns) Environmental violations Social violations Lack of maintenance plans Under-utilization of project Abandonment of project

Locations

Description Kapichira Power Station
District Chikwawa
Region Southern
Street address
Postal code 000

Documents

No records were added

Parties

Description Malawi Government
Locality Lilongwe
Region Central Region
Street address Capital Hill
Postal code 0000
Country Malawi
Telephone 0000
Fax Number 0000
URL www.malawi.gov.mw
Description The Government of Malawi

Contracts

OCID 090143555
External Reference
Title Malawi Energy Restoration Project
Description Kapichira Power Restoration project
Status Active
Contract Value USD 40,000,000.00
Cost Estimate USD 40,000,000.00
Final Value 0.00
Start Date 2022-07-01
End Date 2025-12-31
Max Extent Date
Duration In Days 1279
Procurement Method Limited
Method Details Cost only
Procuring Entity Electricity Generation Company (Malawi) Limited (EGENCO-Blantyre-MW
Administrative Electricity Generation Company (Malawi) Limited (EGENCO-Blantyre-MW

Documents

No records were added

Modifications

No records were added

Budget

Description Kapichira Power Restoration Project - Left bank Desilting
Amount USD 50,000.00
Start Date 2022-08-08
End Date 2022-09-02
Max Extent Date
Duration In Days 25
Party ID World Bank-Washington, DC-US
URI

Project Funding

No records were added
No comments added

Environment

No record was added

Completion

End Date:
End Details:
Final Scope:
Final Scope Details:
Final Value Amount: 0.00
Final Value Details:

Finances

No records were added

Milestones

No records were added

Transactions

No records were added

Benefits

No records were added

Additional Classifications

No records were added

Social

No records were added

Metrics & Forecasts

No records were added

Policy

No record was added

Timelines

Asset Life Time

Start Date 2027-06-16
End Date 2077-06-15
Max End Date