Project
Rehabilitation of old town bus deport under roads fund Administration
Download Project Data
Return
Rehabilitation of old town bus deport under roads fund Administration
Rehabilitation of old town bus deport under roads fund Administration
improving good roads access to the people in lilongwe city.
Start date:
2021-10-11
Due date:
2022-09-12
Approval date:
2021-06-30
Orange Category (7 Red Flags)
Absence of a clear feasibility study
Limited assessment of environmental impacts
Limited assessment of social impacts
Limited assessment of economic impacts
Weak stakeholder engagement
Limited competition
Lack of maintenance plans
1,024,317,687.25 MWK
Total Budget
2022-08-26
Date Created
2022-08-26
Last updated
Rehabilitation
Project Type
Completion
Project Status
Identification
Preparation
Tendering
Implementation
Completion
Maintenance
Decommissioning
ALL
Locations
Parties
Documents
Environment
Locations
Description
contra
District
Lilongwe
Region
Central
Street address
malangalanga and woolian road
Postal code
30396
Documents
No records were added
Parties
Description
Lilongwe City Council
Locality
Lilongwe
Region
Central
Street address
City Center
Postal code
30396
Country
Malawi
Email
[email protected]
Telephone
09000000000
Fax Number
URL
Roles
Procuring entity
Description
LCC Vision is to become a clean, green, and prosperous City.
Contracts
No records were added
Budget
Description
contra
Amount
MWK 1,013,421,421.43
Start Date
2021-10-18
End Date
2022-10-30
Max Extent Date
2022-10-30
Duration In Days
377
Party ID
Lilongwe City Council-Lilongwe-MW
URI
Project Funding
No records were added
FeedBack
Add Feedback
No comments added
Environment
No record was added
Completion
End Date:
2022-09-20
End Details:
The road will be fully upgraded by the said date
Final Scope:
the road will be fully rehabiliteted
Final Scope Details:
Final Value Amount:
MWK 1,024,317,687.25
Final Value Details:
one billion, twenty four million, three hundred and seventeen, six hundred and eighty seven kwacha, twenty five tambala
Finances
No records were added
Milestones
No records were added
Transactions
No records were added
Benefits
No records were added
Additional Classifications
No records were added
Social
No records were added
Metrics & Forecasts
No records were added
Policy
No record was added
Timelines
Asset Life Time
Start Date
2022-09-12
End Date
2032-12-30
Max End Date
Add Feedback
Name
Email
Type
Select Type
Other
Weak Accountability Mechanism
Environmental Violations
Social Violations
Under Utilization Of Project
Abandonment Of Project
Political Interference
Comment
View Map