Chaweta primary school electrical installation


installation of electricity in classrooms and staff houses

improve service delivery

Start date: 2022-07-22 Due date: 2022-09-30 Approval date: 2022-04-01 Orange Category (7 Red Flags)
Absence of a clear feasibility study Limited assessment of environmental impacts Limited assessment of social impacts Limited assessment of economic impacts Weak stakeholder engagement Limited competition Lack of maintenance plans
18,000,000.00   MWK
Total Budget
2022-10-03
Date Created
2023-09-18
Last updated
Construction
Project Type
Completion
Project Status

Locations

No records were added

Documents

No records were added

Parties

No records were added

Contracts

No records were added

Budget

No records were added

Project Funding

No records were added
No comments added

Environment

No record was added

Completion

End Date: 2022-09-22
End Details: COMPLETED
Final Scope: ELECTRIFICATION OF CHAWETA PRIMARY SCHOOL
Final Scope Details: THE PROJECT WAS COMPLETED IN TIME
Final Value Amount: MWK 17,150,000.00
Final Value Details: THERE WAS NO VARRIATION OF COST

Finances

No records were added

Milestones

No records were added

Transactions

No records were added

Benefits

No records were added

Additional Classifications

No records were added

Social

No records were added

Metrics & Forecasts

No records were added

Policy

No record was added

Timelines

Asset Life Time

Start Date 2022-07-30
End Date 2062-09-30
Max End Date 2062-09-30