Construction of 3 TTCs

The Project involves the construction of Three Teacher Training Colleges (TTCs), one in each of the following districts: Mchinji, Chikwawa, and Rumphi; and the project has two lots with a total project cost of MK42 billion with BADEA, Saudi Fund for Development, and OPEC Fund for International Development providing 70% of the resources and Malawi Government providing counterpart funding of 30%.

To increase enrolment of primary school student teachers and improve equitable access to quality education in primary schools

Start date: 2018-01-01 Due date: 2025-03-31 Approval date: 2014-07-01
42,000,000,000.00   MWK
Total Funding
2023-05-17
Date Created
2023-05-17
Last updated
Construction
Project Type
Implementation
Project Status
Absence of a clear feasibility study Unrealistic budgets Limited assessment of environmental impacts Limited assessment of social impacts Limited assessment of economic impacts Weak stakeholder engagement Change of scope Cost overruns and budget inflation Lack of transparency in procurement processes Limited competition Favoritism in bidding processes Political interference Weak accountability mechanisms Frequent project delays (time overruns) Environmental violations Social violations Lack of maintenance plans Under-utilization of project Abandonment of project

Locations

No records were added

Documents

No records were added

Parties

No records were added

Contracts

OCID C.No.025/IPC/MOEST/BADEA/TTCS/CW/001
External Reference
Title Construction of Rumphi TTC
Description • Administration Area: Administration block, Multi-purpose Hall and Kitchen, Student Recreation Centre, Sick bay, Toilet block, Gate House, Landscape Store, General Stores, Generator Room, and Transformer Room; • Teaching Area: Lecture Theatre, 6 Classroom blocks, Special Needs Classroom, Science Laboratory, ICT Laboratory, Library, Language Laboratory and Audio Visual, Workshop for Teaching Material, Maintenance and Metalwork workshop; • Houses (45 Houses): 20 Senior Staff Houses and 15 Semi-detached Staff Houses; • Hostels: 20 Hostels (30 students each hostel), 10 Male Hostels, and 10 Female Hostels; and • Associated External Works: Landscape, Road Works, Boundary Wall and Walkways.
Status Active
Contract Value USD 11,292,887.37
Cost Estimate USD 11,292,887.37
Final Value 0.00
Start Date 2018-01-10
End Date 2024-03-31
Max Extent Date
Duration In Days 2272
Procurement Method Open
Method Details Best value to government
Procuring Entity Ministry of Education-Lilongwe-MW
Administrative Directorate of Buildings (DoB)-Lilongwe-MW

Documents

No records were added

Modifications

No records were added
OCID C.No.025/IPC/MOEST/BADEA/TTCS/CW/002
External Reference
Title Construction of Mchinji TTC
Description • Administration Area: Administration block, Multi-purpose Hall and Kitchen, Student Recreation Centre, Sick bay, Toilet block, Gate House, Landscape Store, General Stores, Generator Room, and Transformer Room; • Teaching Area: Lecture Theatre, 6 Classroom blocks, Special Needs Classroom, Science Laboratory, ICT Laboratory, Library, Language Laboratory and Audio Visual, Workshop for Teaching Material, Maintenance and Metalwork workshop; • Houses (45 Houses): 20 Senior Staff Houses and 15 Semi-detached Staff Houses; • Hostels: 20 Hostels (30 students each hostel), 10 Male Hostels, and 10 Female Hostels; and • Associated External Works: Landscape, Road Works, Boundary Wall and Walkways.
Status Active
Contract Value USD 11,711,999.87
Cost Estimate USD 11,711,999.87
Final Value 0.00
Start Date 2018-01-10
End Date 2024-03-31
Max Extent Date
Duration In Days 2272
Procurement Method Open
Method Details Best value to government
Procuring Entity Ministry of Education-Lilongwe-MW
Administrative Directorate of Buildings (DoB)-Lilongwe-MW

Documents

No records were added

Modifications

No records were added
OCID C.No.025/IPC/MOEST/BADEA/TTCS/CW/003
External Reference
Title Construction of Chikwawa TTC
Description • Administration Area: Administration block, Multi-purpose Hall and Kitchen, Student Recreation Centre, Sick bay, Toilet block, Gate House, Landscape Store, General Stores, Generator Room, and Transformer Room; • Teaching Area: Lecture Theatre, 6 Classroom blocks, Special Needs Classroom, Science Laboratory, ICT Laboratory, Library, Language Laboratory and Audio Visual, Workshop for Teaching Material, Maintenance and Metalwork workshop; • Houses (45 Houses): 20 Senior Staff Houses and 15 Semi-detached Staff Houses; • Hostels: 20 Hostels (30 students each hostel), 10 Male Hostels, and 10 Female Hostels; and • Associated External Works: Landscape, Road Works, Boundary Wall and Walkways
Status Active
Contract Value USD 11,616,853.53
Cost Estimate USD 11,616,853.53
Final Value 0.00
Start Date 2018-01-15
End Date 2024-03-31
Max Extent Date
Duration In Days 2267
Procurement Method Open
Method Details Best value to government
Procuring Entity Ministry of Education-Lilongwe-MW
Administrative Directorate of Buildings (DoB)-Lilongwe-MW

Documents

No records were added

Modifications

No records were added

Budget

No records were added

Project Funding

No records were added
No comments added

Environment

No record was added

Completion

End Date:
End Details:
Final Scope:
Final Scope Details:
Final Value Amount: 0.00
Final Value Details:

Finances

No records were added

Milestones

No records were added

Transactions

No records were added

Benefits

No records were added

Additional Classifications

No records were added

Social

No records were added

Metrics & Forecasts

No records were added

Policy

No record was added

Timelines

Asset Life Time

Start Date 2024-03-31
End Date 2074-03-31
Max End Date 2075-03-31