Construction of senior chief Lukwa house

Construction of senior chief Lukwa house

To promote local governance through provision of chief housing

Start date: 2023-01-09 Due date: 2023-06-30 Approval date: 2019-02-01
62,597,322.30   MWK
Total Funding
2023-05-17
Date Created
2023-05-17
Last updated
Construction
Project Type
Implementation
Project Status
Absence of a clear feasibility study Unrealistic budgets Limited assessment of environmental impacts Limited assessment of social impacts Limited assessment of economic impacts Weak stakeholder engagement Change of scope Cost overruns and budget inflation Lack of transparency in procurement processes Limited competition Favoritism in bidding processes Political interference Weak accountability mechanisms Frequent project delays (time overruns) Environmental violations Social violations Lack of maintenance plans Under-utilization of project Abandonment of project

Locations

Description Construction of a dwelling house
District Kasungu
Region Central
Street address
Postal code

Documents

Title Signed agreement form
Description A signed agreement form between Kasungu district council and a contractor
Document Type Signed Contract
Date Published
Date Modified
Language
Page Start
Page End
Author
Access Details

Parties

Description Kasungu District Council
Locality Kasungu
Region Central
Street address Private Bag 1, Kasungu
Postal code Located within Kasungu Municipality
Country Malawi
Telephone +265253314
Fax Number +265253314
URL
Description Discription

Contracts

OCID 001/4109/02/22/107
External Reference
Title Construction of Senior Chief Lukwa House
Description construction of Senior Chief Lukwa house
Status Active
Contract Value MWK 62,597,322.30
Cost Estimate MWK 62,597,322.30
Final Value 0.00
Start Date 2023-01-09
End Date 2023-06-30
Max Extent Date
Duration In Days 172
Procurement Method Open
Method Details Best value to government
Procuring Entity Kasungu District Council-Kasungu-MW
Administrative Kasungu District Council-Kasungu-MW

Documents

No records were added

Modifications

No records were added

Budget

Description Construction of Chief Lukwa house
Amount MWK 54,178,428.50
Start Date 2023-01-09
End Date 2023-06-30
Max Extent Date
Duration In Days 172
Party ID Kasungu District Council-Kasungu-MW
URI

Project Funding

Party Malawi Government-Lilongwe-MW
Amount MWK 62,597,322.30
Description construction of Senior Chief Lukwa house
Party Malawi Government-Lilongwe-MW
Amount MWK 62,597,322.30
Description construction of Senior Chief Lukwa House
No comments added

Environment

No record was added

Completion

End Date:
End Details:
Final Scope:
Final Scope Details:
Final Value Amount: 0.00
Final Value Details:

Finances

No records were added

Milestones

No records were added

Transactions

No records were added

Benefits

No records were added

Additional Classifications

No records were added

Social

No records were added

Metrics & Forecasts

No records were added

Policy

No record was added

Timelines

© 2025, Construction Sector Transparency Initiative (CoST Malawi). All Right Reserved;

All content on the platform is licensed under Creative Commons Attribution 4.0 Unported License.