SECONDARY EDUCATION IN MALAWI (ISEM II) PROJECT
ISEM II Project aims at upgrading and expanding secondary school infrastructure, and expanding technical vocational education facilities in secondary schools, including improved WASH facilities and climate resilient infrastructure. The upgrading and expansion of secondary schools, focuses on infrastructure works for selected CDSSs in the original six (6) ISEM I demonstration districts and six (6) additional districts. The Project will run from 2021 to 2025.
aims at upgrading and expanding secondary school infrastructure, and expanding technical vocational education facilities in secondary schools, including improved WASH facilities and climate resilient infrastructure
Start date: 2021-07-01
Due date:
2025-12-31
Approval date: 2021-07-01
Absence of a clear feasibility study
Unrealistic budgets
Limited assessment of environmental impacts
Limited assessment of social impacts
Limited assessment of economic impacts
Weak stakeholder engagement
Change of scope
Cost overruns and budget inflation
Lack of transparency in procurement processes
Limited competition
Favoritism in bidding processes
Political interference
Weak accountability mechanisms
Frequent project delays (time overruns)
Environmental violations
Social violations
Lack of maintenance plans
Under-utilization of project
Abandonment of project