image

Chituka Dispensary equipment

The community will have no more problem of traveling long distance to acquire the health services

The community will have no more problem of traveling long distance to acquire the health services

Start date: 2022-05-05 Due date: 2022-06-05 Approval date: 2022-02-05
8,059,460.00   MWK
Total Funding
2023-06-05
Date Created
2023-06-06
Last updated
Replacement
Project Type
Completion
Project Status
Absence of a clear feasibility study Unrealistic budgets Limited assessment of environmental impacts Limited assessment of social impacts Limited assessment of economic impacts Weak stakeholder engagement Change of scope Cost overruns and budget inflation Lack of transparency in procurement processes Limited competition Favoritism in bidding processes Political interference Weak accountability mechanisms Frequent project delays (time overruns) Environmental violations Social violations Lack of maintenance plans Under-utilization of project Abandonment of project

Locations

No records were added

Documents

No records were added

Parties

No records were added

Contracts

OCID 537
External Reference NB/DC/GESD/2021/22/10/4
Title Chituka Dispensary equipment
Description procurement of Chituka Dispensary equipment
Status Active
Contract Value MWK 8,059,460.00
Cost Estimate MWK 8,059,460.00
Final Value 0.00
Start Date 2022-03-14
End Date 2022-04-14
Max Extent Date
Duration In Days 31
Procurement Method Open
Method Details Lowest cost
Procuring Entity Nkhatabay District Council-Nkhatabay-MW
Administrative Nkhatabay District Council-Nkhatabay-MW

Documents

No records were added

Modifications

No records were added

Budget

No records were added

Project Funding

No records were added
No comments added

Environment

No record was added

Completion

End Date: 2022-06-22
End Details: The hospital is now under full operation
Final Scope: The community will have no more problem of traveling long distance to acquire the health services
Final Scope Details: The community will have no more problem of traveling long distance to acquire the health services
Final Value Amount: MWK 8,059,460.00
Final Value Details: reduction in deaths and mobility challenge

Finances

No records were added

Milestones

No records were added

Transactions

No records were added

Benefits

No records were added

Additional Classifications

No records were added

Social

No records were added

Metrics & Forecasts

No records were added

Policy

No record was added

Timelines

Asset Life Time

Start Date 2022-06-05
End Date 2048-06-05
Max End Date 2048-06-05