REHABILITATION OF COUNCIL CHAMBER

rehabilitation of council chamber at Zomba District Council offices

to create a conducive environment for hosting meetings

Start date: 2023-03-01 Due date: 2023-06-30 Approval date: 2022-08-12
25,209,391.19   MWK
Total Funding
2023-09-06
Date Created
2023-09-06
Last updated
Rehabilitation
Project Type
Implementation
Project Status
Absence of a clear feasibility study Unrealistic budgets Limited assessment of environmental impacts Limited assessment of social impacts Limited assessment of economic impacts Weak stakeholder engagement Change of scope Cost overruns and budget inflation Lack of transparency in procurement processes Limited competition Favoritism in bidding processes Political interference Weak accountability mechanisms Frequent project delays (time overruns) Environmental violations Social violations Lack of maintenance plans Under-utilization of project Abandonment of project

Locations

Description rehabilitation of Council Chamber
District Zomba
Region Southern
Street address 0000
Postal code 23

Documents

Title REHABILITATION OF COUNCIL CHAMBER signed contract
Description signed contract between Zomba District Council and Marshall construction
Document Type Signed Contract
Date Published
Date Modified
Language
Page Start
Page End
Author
Access Details
Title REHABILITATION OF COUNCIL CHAMBER sign post
Description sign post
Document Type Defaults
Date Published
Date Modified
Language
Page Start
Page End
Author
Access Details
Title REHABILITATION OF COUNCIL CHAMBER
Description physical progress report
Document Type Physical progress reports
Date Published
Date Modified
Language
Page Start
Page End
Author
Access Details

Parties

Description Zomba District Council
Locality Zomba
Region Southern Region
Street address Box 43
Postal code
Country Malawi
Telephone 00000000
Fax Number
URL
Description Zomba District Council
Description Malawi Government
Locality Lilongwe
Region Central Region
Street address Capital Hill
Postal code 0000
Country Malawi
Telephone 0000
Fax Number 0000
URL www.malawi.gov.mw
Description The Government of Malawi

Contracts

OCID RFQ/ZADC/DDF/2022/2023/02
External Reference
Title REHABILITATION OF COUNCIL CHAMBER CONTRACT
Description Signed contract between marshall construction company and Zomba District Council
Status Active
Contract Value MWK 25,209,391.19
Cost Estimate MWK 25,209,391.19
Final Value 0.00
Start Date 2023-03-01
End Date 2023-05-30
Max Extent Date 2023-06-30
Duration In Days 121
Procurement Method Direct
Method Details Lowest cost
Procuring Entity Zomba District Council-Zomba-MW
Administrative Zomba District Council-Zomba-MW

Documents

No records were added

Modifications

No records were added

Budget

No records were added

Project Funding

Party Malawi Government-Lilongwe-MW
Amount MWK 25,209,391.19
Description funded under DDF
No comments added

Environment

No record was added

Completion

End Date:
End Details:
Final Scope:
Final Scope Details:
Final Value Amount: 0.00
Final Value Details:

Finances

No records were added

Milestones

No records were added

Transactions

No records were added

Benefits

No records were added

Additional Classifications

No records were added

Social

No records were added

Metrics & Forecasts

No records were added

Policy

No record was added

Timelines

Asset Life Time

Start Date 2023-07-30
End Date 2035-07-30
Max End Date 2037-07-30