Construction of 3 No. Block of 2 bedroom Flats at Nandolo in Zomba


3 No. 2 bedroom Flats

Providing Safety ,Comfort and affordable to the Nation

Start date: 2019-03-28 Due date: 2020-05-30 Approval date: 2020-02-01 Orange Category (7 Red Flags)
Absence of a clear feasibility study Limited assessment of environmental impacts Limited assessment of social impacts Limited assessment of economic impacts Weak stakeholder engagement Limited competition Lack of maintenance plans
739,244,998.15   MWK
Total Budget
2023-09-07
Date Created
2023-09-11
Last updated
Construction
Project Type
Decommissioning
Project Status

Locations

No records were added

Documents

No records were added

Parties

No records were added

Contracts

No records were added

Budget

No records were added

Project Funding

No records were added
No comments added

Environment

No record was added

Completion

End Date: 2020-05-30
End Details: The contract was terminated due to Non Performance by the contractor -New Contractors will be identified to complete the works.
Final Scope:
Final Scope Details:
Final Value Amount: MWK 488,839,492.06
Final Value Details:

Finances

No records were added

Milestones

No records were added

Transactions

No records were added

Benefits

No records were added

Additional Classifications

No records were added

Social

No records were added

Metrics & Forecasts

No records were added

Policy

No record was added

Timelines